Support
Machine type
Brand
BBC Forced Air and Aeolus Conveyor DTG Dryers

BBC Forced Air and Aeolus Conveyor DTG Dryers support

Covers: BBC Forced Air 24 in (FA-244) · 36 in (FA-364) · Aeolus (AIR-366C)

BBC Industries' Forced Air dryers and the Aeolus combine infrared heaters with a blower that pushes fresh, hot, dry air through the chamber, which is what water-based and DTG inks need. Both have two heat zones, with Zone 1 set hotter than Zone 2, and a conveyor control set as time in the chamber. They are hardwired to a dedicated disconnect by an electrician. Start here for settings, troubleshooting and the manuals.

BBC Industries Forced Air 2408 conveyor DTG dryer on its stand

Setup & first print

Troubleshooting

Techniques & settings

Manuals & downloads

Watch BBC Industries's video: BBC Aeolus conveyor dryer overview

Embedded from the manufacturer's official channel.

About the BBC Forced Air and Aeolus Conveyor DTG Dryers

In these dryers the blower brings warm, dry air up from the dryer floor and out through holes in the heating elements, so humid air is pushed out instead of recirculated. The blower can't be switched off, because it also keeps the outside of the oven cool. Two temperature dials let you run a plateau profile: a hot first zone brings the shirt up to cure temperature quickly, and a cooler second zone holds it there without scorching.

Key specs

Forced Air 24 in / 36 in Aeolus
Belt width 24 in or 36 in 36 in, 72 in chamber
Power 240 V or 208 V, single or three phase. 24 in: 7.2 kW at 240 V. 36 in: 10.9 kW at 240 V 240 V, single or three phase, check the power label on your dryer
Connection No cord supplied. Hardwired to a dedicated disconnect No cord supplied. Wired to the disconnect in the top control panel
Conveyor control Digital, set by chamber time Shown as time through the tunnel, MM:SS

Maintenance at a glance

When What to do
Every run Keep the conveyor moving whenever the heat is on
At installation, 30 days and 120 days With power locked out, an electrician checks that every terminal in the control panel is tight
Forced Air: 1 week after install, then monthly Re-tighten the supply terminal set screws until they no longer loosen, then check periodically

Where to put it

Both need a dedicated circuit disconnect with branch protection, a proper earth ground, and a certified electrician to connect them under local code. Keep drafts away from the chamber: open doors, air conditioners and fans pointed at the oven all make the temperature swing. Never use it where gasoline, paint or other flammable vapors are stored.