Short answer

Turn the belt on before the heat, and keep it moving while the heaters are above 300°F. The controller reads the heater, not the shirt, so the set point is hundreds of degrees above cure temperature. Vastex's starting profile for DTG on an X2D (Epson and Brother printers with pretreat) is BOOST 905°F and MAIN 500°F for 2 to 3.5 minutes in the heat. Confirm with a heat gun on the ink at the exit, still under the last heater.

Start-up, in this order

  1. Power on at the main disconnect

    The red Power light comes on.

  2. Check the belt path

    Remove anything left on the belt or in the chamber.

  3. System switch on

    This powers the controls, belt speed control and exhaust blower.

  4. Conveyor on

    Set the belt speed you plan to run.

  5. Heat switch on, set the temperature

    Hold the up arrow to raise the set value. Allow about 15 minutes to heat up.

Keep the belt moving whenever the heaters are above 300°F (149°C). Never leave the dryer running unattended.

Three things set your cure

Set point. The sensor sits right under the heater, so it reads far hotter than the garment. Set several hundred degrees above the ink's cure temperature, then check the real ink temperature. Heater height. Loosen the knobs on the side and raise or lower each side of the heater. Belt speed. The meter shows volts to the belt motor, not seconds. Use the table for your model, then time it yourself: put a small metal object on the edge of the belt and time it from the chamber entrance to the exit.

Volts X1-30 time in chamber X2-30 time in chamber
90 V 18 s 12 s
60 V 27 s 20 s
40 V 33 s 30 s
30 V 56 s 40 s
20 V 87 s 62 s
10 V 180 s 135 s

These are Vastex's figures for common sprocket and motor setups. Yours may differ, which is why the timing test matters.

Vastex starting profiles for the X2-D

Profile BOOST MAIN Heater height settings Use
2 to 3.5 minutes 905°F (485°C) 500°F (260°C) 4.5 and 3.5 Epson, Brother and other DTG printers using pretreat with DuPont white ink. Vastex notes 2.5 to 3 minutes wash tested well
3.5 to 4 minutes 860°F (460°C) 525°F (274°C) 3.5 and 3 Inks and materials needing up to 4 minutes. If it overheats, lower the MAIN zone

Vastex calls these starting points only: shop temperature, humidity, ink brand and shirt all change the result. For the X2D and X3D, Vastex's general guidance for 2 to 4 minute cures is BOOST at 800°F or more and MAIN at 500°F or more, with BOOST always equal to or higher than MAIN.

Confirm the cure

Check ink temperature regularly with a non-contact heat gun, aiming at the ink while it is still under the last heater, toward the outside of the image. A heat gun reads only the top of the ink, so allow extra on thick white underbases. Then compare with your ink maker's cure temperature and do a wash test.

Shut-down

Turn the heat switch off and let the dryer cool to 300°F or below with the belt running. Then turn the belt speed down (optional), switch the system switch to STOP, and turn off the main disconnect. Do this at the end of every shift.

Watch Vastex's video: The importance of using a donut probe

More videos

Introduction of the LittleRed X1-D DTG dryer
Brother GTX curing on a Vastex LittleRed X3-D

Embedded from the manufacturer's official channel.

Common questions

Is there a Vastex DTG profile for the X1 or X2 without the D?

Vastex's published DTG profile is for the X2-D. On single-zone models, start from your ink maker's cure temperature and time, set the time in the chamber with the belt speed table, and check the ink temperature at the exit. Text us and we'll help you set it up.

Can I cure DTF transfers in a LittleRed?

Vastex doesn't publish DTF settings for the LittleRed, and Color Prime lists its cure temperatures for shaker ovens and desktop curing ovens. Talk to us before running DTF film through a conveyor dryer.

Can I cure pretreatment in the dryer?

Vastex doesn't publish pretreatment settings for the LittleRed. Follow your pretreatment maker's instructions and contact us if you want to try it in the dryer.

How long does it take to heat up?

About 15 minutes to reach 700 to 800°F.

I'm taking a break. Should I turn the heat off?

If no garments will go through for more than 10 minutes, Vastex recommends lowering the set point to 500°F. It takes about 10 minutes to come back to operating temperature. Keep the belt running.